Canvey Railway and Model Engineering Club.

It's NOT a swimming pool!
26-07-23

(sorry, but this is a long story)

There was once a tiny puddle very close to the fire hydrant, so it got reported and this is the story of that tiny puddle.
In the background you can see the
leak from around the fire hydrant
So the men in hard hats came

12 April 2023

came out to fix it

26 April 2023

And left it like this.

26 April 2023

Big hole and a large mound of earth.

Its stayed this way for two weeks then suddenly it got bigger and extra shuttering and even more water was escaping

(see 4 June)

Moving on to the 10 May 2023 it had moved on this far
Same day different angle

4 June 2023

Its now turned into a "HUGE" hole.

4 June 2023

which has loads of water in it.

4 June 2023

We STILL cant drive passed that gap.

11 June 2023

Nothing's happening yet

14 June 2023

If you look closely you can see

14 June 2023

water movement from the leak

14 June 2023

The edges of the hole has collapsed

21 June 2023

Less water in the hole as it was pumped on to the, inner track

21 June 2023

basin of our field causing flooding to the field and not for the first

21 June 2023

time.That mesh is even nearer, still stopping the trains from running.

02 July 2023

The nice men in hard hats to these next four pictures as it was a work

02 July 2023

site. This is the first and smaller hole to the left of the bigger hole.

02 July 2023

As you can see this is much clearer than the smaller hole.

To stop further collapse of the edge of the hole the men in hard hats have,

driven shuttering into the ground to help support the ground underneath the track and try to stop further landslides.

02 July 2023

How close the hole came to the edge of our raised track.

05 July 2023

More works happens to the hole. Water is now being bypassed by the

05 July 2023

blue pipe. There's now shuttering to protect the track.

05 July 2023

A very muddy hole, that's still oozing water from somewhere.

16 July 2023

Don't panic this is not water from the pipe its rain water.

16 July 2023

The shutting has been cut down. Because this hole

16 July 2023

is lower than the ground around it all the water drains into it.

 

In the space of 6 days, there was a concerted push by the men in hard hats to finish the the new pipe work and fill in the hole.

 

.

The hole is gone,

it's finally filled in,

it's been covered over,

its been buried.

Our trains can now drive past as the hole's gone. All it needs now is some grass seed to be laid down.

"YAY"

19 July 23

19 July 23

 

It's NOT swimming water!